Ross Bridge update from Cornwall Council 20/01/26

Published: 22nd January 2026 in category: Penzance, Project Updates

Work to refurbish Ross Bridge in Penzance began on 5th January 2026. The project by Cornwall Council was originally expected to take 13 weeks.

Following a pause in work over the last week, Cornwall Council provided this update on Tuesday 20 January:

“During last week’s work to dismantle Ross Bridge so that it can be refurbished, our team discovered active pigeon nests within the structure. As with all wild birds, their nests and eggs are protected by law, and we immediately paused work.

“Ecological surveys carried out before Christmas showed no signs of nesting, so it appears the pigeons moved in over the holiday period. Our ecological specialist has been monitoring the nest since its discovery, and a further survey this morning confirmed the nest had been abandoned and the eggs were not viable. The nest has now been safely removed.

“With this confirmation, works will now continue. We’re committed to progressing the project as efficiently as possible and will be bringing in additional resources to help recover lost time.”

Recent News & Events Posts

Our Partners & Who We Support

Cornwall Council & Safer Penzance Logos
Penzance BID and Sustainable Penzance logos
Penzance Town Deal and Kerbs Skateboard Association logos
Penlee Park and Town Council logos
Friends of Penzance Jewish Cemetery and Friends of Penlee House logos
Ross Bridge update from Cornwall Council 20/01/26
Trelya and Citizens Advice Cornwall logos
Newlyn Harbour and The Centre logos
YMCA Cornwall and Cornish Maritime Trust logos
Jubilee Pool logos
Solomon Browne Memorial Hall and Growing Links logos
West Cornwall Women's Aid and Redwing logos
Mousehole Rock Pool and Newlyn Art Gallery logos
Newlyn Harbour Lights and Bewnans Kernow logos
St Piran and Montol logos
Penzance Youth and Penzance Literary Festival logos